New: Document Integrations are live. See what your AI can read now

Earned value management software

Earned value, from the whole project to a single activity.

Every standard earned value metric, calculated from your schedule by cost or by units, so you can see the moment cost or schedule performance starts to slip.

DC Echo EVM
Cost basis
SPI
0.63
CPI
0.81
TCPI
0.85
EAC
$27.9M
$30M$20M$10M0Jul 2025Jan 2026Jul 2026Jan 2027Jul 2027Data dateForecast over budget

Why teams choose it

Three reasons it earns its place.

01

Every metric, calculated for you.

PV, EV, AC, SPI, CPI, EAC, VAC and TCPI, worked out with the standard formulas, at every level of the project.

Standard EVM formulas
02

By cost or by units.

Measure performance in money or in resource and expense units, whichever fits how the work is managed.

Cost or units
03

Slippage spotted early.

SPI and CPI at the data date for every WBS, so underperforming packages stand out before the monthly report.

Every WBS, every update

Technical specification

Standard earned value, at every level.

Metrics
PV, EV, AC, SPI (EV/PV), CPI (EV/AC), ETC, EAC (AC + ETC), BAC, VAC (BAC − EAC) and TCPI
Basis
Cost, or resource and expense units
Levels
Whole project, every WBS level and single activities
Charts
S-curves for planned value, earned value and actual cost
Units views
Daily histogram against budget, and cumulative S-curve against the baseline
WBS table
Units progress, physical progress, and SPI and CPI at the data date

The metrics

The standard formulas, nothing hidden.

Every figure traces back to planned value, earned value and actual cost, so your team and your client read the numbers the same way.

  • Standard formulas
  • Project to activity
  • Traceable to PV, EV, AC
PV
Planned value
EV
Earned value
AC
Actual cost
SPI
EV / PV
CPI
EV / AC
ETC
Estimate to complete
EAC
AC + ETC
BAC
Budget at completion
VAC
BAC − EAC
TCPI
To-complete performance index

By WBS

See which packages are pulling performance down.

SPI and CPI at the data date sit beside units and physical progress for every WBS, so the weakest packages are obvious.

  • Cost or units
  • SPI and CPI per WBS
  • Physical progress
Earned value by WBS
Cost
Units
WBS
UNITS
PHYSICAL
SPI
CPI
DC Echo
21.6%
34.5%
0.63
0.81
Design
38.6%
55.2%
1.00
0.24
Procurement
0%
54.0%
0
–
Construction
2.0%
11.8%
0.12
0.82
Site setup
100%
100%
1.00
0.35

Daily view

Spot the days work went over budget.

Switch to units and the daily view shows, day by day, how much was used within budget, how much budget went unused and how much went over.

  • Daily histogram
  • Cumulative S-curve
  • Against the baseline
Daily units, against budget
Within budget
Unused budget
Over budget

FAQ

Questions, answered.

Technical questions about earned value.

Talk to our team

PV, EV and AC, plus SPI (EV/PV), CPI (EV/AC), ETC, EAC (AC + ETC), BAC, VAC (BAC − EAC) and TCPI.

Yes. Every metric is available based on cost or on resource and expense units.

From the whole project down through every WBS level to a single activity.

S-curves for planned value, earned value and actual cost, plus daily and cumulative views when working in units.