Iron ore plant, mining
Acceleration

A 33% faster shutdown on an iron ore plant.

33%
faster shutdown
40 days
off the shutdown plan
$18.2M
in projected savings
The decision

“Where do we protect the plan, and where do we push?”

  1. The challenge

    Every day of delay on the shutdown was worth $455K.

  2. What Nodes & Links showed

    Early visibility into risk showed where to protect and where to push.

  3. The result

    An 80-day shutdown plan instead of 120, for $18.2M in projected savings.

120 days down to 80.

Original plan
120 days
With Nodes & Links
80 days
Under the hood
Schedule Optimizer
Opportunities & Threats
PAD

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.