01
A forecast based on evidence.
PAD compares how long completed activities really took against plan, then applies that to the work still to come.
Actual ÷ planned
Use cases
By organization
Featured stories
Latest from the blog
AI with full project context: Connect Nodes & Links with AconexNovember 5, 2026All blog posts →Featured guide
GuideThe Executive Guide to AI for Project DeliveryTest date confidence, understand project risk and focus interventions, with auditable evidence.Read the guide →All guides →Watch, read and learn
WebinarsLive sessions and on-demand replays.WhitepapersLong reads on where project delivery is going.ResearchThe peer-reviewed work behind the models.Platform coursesShort videos on getting more from the platform.The Physics of Project AccelerationOur book on pulling project dates forward.All resources →Platform / Ground truth models / PAD Prediction
Schedule delay forecasting
PAD Prediction uses the actual performance of completed activities to forecast how long remaining work will take, and how late every WBS will finish.
Why teams choose it
PAD compares how long completed activities really took against plan, then applies that to the work still to come.
See the predicted delay for every WBS or activity code, so the areas most likely to overrun are obvious.
Click any forecast to see the completed activities behind it, and export them to justify the delay to anyone.
Technical specification
The basis
Click a PAD value to see which WBS or activity code level was used, the completed activities included and each one’s actual PAD, ready to export.
By activity
Every remaining activity gets a predicted duration, increase and finish date, so you know exactly where to focus mitigation.
By WBS
Total delay sits beside every WBS or activity code node, so you can compare areas and drill into the one that needs attention.
Performance Against Duration: actual duration divided by planned duration, averaged across similar completed activities in the same WBS or activity code.
The applied PAD is multiplied by the planned duration of each remaining activity, giving a predicted duration, finish date and delay for every activity and every WBS.
PAD needs enough completed activities to be meaningful, so it moves up the hierarchy until there’s enough evidence to forecast.
Yes. Click any PAD value to see the completed activities it was calculated from, and export that list to Excel.