The real drivers, ranked.
The top 20 activities and risk events behind any P-position, split into duration uncertainty and risk events.
Top 20 drivers
Use cases
By organization
Featured stories
Latest from the blog
AI with full project context: Connect Nodes & Links with AconexNovember 5, 2026All blog posts →Featured guide
GuideThe Executive Guide to AI for Project DeliveryTest date confidence, understand project risk and focus interventions, with auditable evidence.Read the guide →All guides →Watch, read and learn
WebinarsLive sessions and on-demand replays.WhitepapersLong reads on where project delivery is going.ResearchThe peer-reviewed work behind the models.Platform coursesShort videos on getting more from the platform.The Physics of Project AccelerationOur book on pulling project dates forward.All resources →Platform / Ground truth models / Risk drivers
Schedule risk driver analysis
Risk drivers ranks the activities and risk events behind any P-position, for any activity, straight from your QSRA results, so mitigation goes where it counts.
Why teams choose it
The top 20 activities and risk events behind any P-position, split into duration uncertainty and risk events.
Normalized shares that add to 100%, converted to days using the P80 delay, or raw correlation when you need it.
Compare drivers with the previous update or your mitigation scenario, and see which risks are actually coming down.
Technical specification
The math
Raw correlations are normalized so the drivers add to 100%, then converted to days using the target’s P80 delay, so the numbers are always explainable.
Mitigation
Turn on the mitigation comparison to see each driver before and after your mitigation scenario, and spot the risks that still need attention.
Two lenses
Look at which activities drive the risk, or which risk events do and where they hit, then search for project-wide drivers in one click.
From the Monte Carlo results. The target activity’s finish delay in each iteration is correlated with every other activity’s change in duration, with duration uncertainty and risk events measured separately.
The correlations are normalized so the drivers add up to 100%. The top 20 are shown, and the rest are grouped as one additional figure.
Each normalized percentage is multiplied by the target activity’s P80 delay. A 37.5% driver on a 200-day P80 delay is 75 days.
Yes. Switch off normalization to see each driver’s raw correlation coefficient as a percentage. Raw values don’t add up to 100%.