Customer stories / Industrial energy plant

Industrial energy · Project team
Risk and forecasting

The schedule moved 24 days. The risk picture moved 281.

281 days
movement in the P50 date
24 days
movement in the schedule itself
83%
of exposure from duration uncertainty
The decision

“What changed in our P50 date between the last two updates, and what is driving it?”

  1. The challenge

    The P50 date moved sharply between two updates, and the team needed to know why.

  2. What Nodes & Links showed

    AI Mode compared the two risk runs and broke down what drove the change.

  3. The result

    Most of the exposure came from uncertainty in activity durations, not named risks, so the team could focus mitigation where the risk really sat.

Under the hood
QSRA
QCRA
Opportunities & Threats

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.