Customer stories / Electricity grid owner

Electricity grid · Owner
Disputes and claims

A clear contract position on a 112-day slip.

112 days
completion moved in one update
7 to 140
critical path activities
848
logic changes in a single revision
The decision

“Compare this month’s contractor schedule with last month’s, and give me a conclusion for each chart.”

  1. The challenge

    A contractor’s monthly schedule pushed completion out by 112 days.

  2. What Nodes & Links showed

    AI Mode compared this month’s schedule with last month’s and drew a conclusion for each chart.

  3. The result

    The owner had the evidence to respond under its NEC4 contract and ask for credible corrective measures.

Under the hood
Delay Navigator
Change History
Change Control

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.