Delay recovery

Steel slips 2 months. Can we still finish on time?

51 days
gap to close
28 days
from compressing downstream work
15 to 17
more days from a 6-day week
The decision

“If steel erection slips 2 months, how do we still finish on time? A 6-day week is an option for some trades.”

  1. The challenge

    Steel erection was set to slip 2 months, putting the finish date at risk.

  2. What Nodes & Links showed

    AI Mode tested recovery scenarios against the live schedule, including a 6-day week for steel trades.

  3. The result

    Together the two levers close almost all of the 51-day gap, so the team started the completion date conversation early.

Under the hood
Delay Navigator
Schedule Optimizer
Critical path

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.