Customer stories / Data center owner

Data centers · Owner
Change management

A new submission reviewed before it was accepted.

+114 days
added to the critical path
869
activities changed in one update
123 vs 13
activities longer vs. shorter
The decision

“Is there anything to worry about in the May submission compared with April?”

  1. The challenge

    A new monthly submission was waiting for the owner to accept it.

  2. What Nodes & Links showed

    AI Mode compared the May submission with April, activity by activity.

  3. The result

    The critical path grew from 249 to 363 days. The owner had a specific list of changes to question before accepting the submission.

Under the hood
Change Control
Change History
Critical path

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.