Customer stories / Data center program contractor

Data centers · Contractor
Acceleration

Testing a faster plan against your own track record.

252 days
average trench work on completed projects
94 to 103
days planned on two upcoming projects
7 projects
in the benchmark
The decision

“How long does trench work take us on average, across all our projects?”

  1. The challenge

    Two upcoming projects planned trench work far faster than anything the team had delivered before.

  2. What Nodes & Links showed

    Global AI benchmarked the new plans against how long trench work really took across seven of the team’s own projects.

  3. The result

    Both plans allowed less than half the benchmark, and both were flagged for review before work started, using the company’s own data as the yardstick.

Under the hood
Schedule Optimizer
Opportunities & Threats
PAD

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.