Customer stories / Energy facility

Energy, design phase
Progress verification

A 70% shortfall hiding behind a “healthy” SPI.

1.01
reported SPI
9 of 30
planned deliverables issued
70%
execution shortfall caught
The decision

“Is the progress being reported real?”

  1. The challenge

    Performance metrics looked healthy, with an SPI of 1.01.

  2. What Nodes & Links showed

    Progress Tracking compared reported progress with what was delivered.

  3. The result

    Only 9 of 30 deliverables had gone out. Caught before the next month.

What the SPI didn’t show.

Planned
30 deliverables
Actually issued
9
Under the hood
Progress Tracking
EVM
PAD

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.