WebinarsLive sessions and on-demand replays.WhitepapersLong reads on where project delivery is going.ResearchThe peer-reviewed work behind the models.Platform coursesShort videos on getting more from the platform.The Physics of Project AccelerationOur book on pulling project dates forward.All resources →Customer stories / Data center owner
“Is there anything to worry about in the May submission compared with April?”
A new monthly submission was waiting for the owner to accept it.
AI Mode compared the May submission with April, activity by activity.
The critical path grew from 249 to 363 days. The owner had a specific list of changes to question before accepting the submission.
Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.
They’re listed under “Under the hood” on this page, with a link to the full use case.
Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.
On the Customers page, where you can filter every story by use case.