Customer stories / Oil and gas owner

Oil and gas · Owner
Progress verification

Reported progress, checked against the schedule in minutes.

89%
of hours earned, as reported
79.9%
in the report’s own tables
10 weeks
behind the original baseline
The decision

“Compare the schedule’s progress to the contractor’s weekly report. Where do they disagree?”

  1. The challenge

    The contractor’s weekly report claimed 89% of hours earned.

  2. What Nodes & Links showed

    AI Mode compared the schedule’s progress with the report, line by line.

  3. The result

    The report’s own tables showed 79.9%, about 10 weeks behind baseline. The owner raised six specific points, starting with a recovery plan for the largest subcontractor.

Under the hood
Progress Tracking
EVM
PAD

FAQ

Questions, answered.

About this customer story.

Talk to our team

Yes. Every story comes from a real customer project. Some are anonymized to protect sensitive programs.

They’re listed under “Under the hood” on this page, with a link to the full use case.

Every project is different, but the same models and AI Mode are available to every customer. Book a demo to see them on projects like yours.

On the Customers page, where you can filter every story by use case.